Architect:
Dugan Morris Architects
Main contractor:
Kier Group
Location:
King’s Cross, London, UK
Working_time:
From September 2015 to April 2017
Project_info:
Unitized curtain wall from L01 to roof.
Stick steel Raico curtain wall in ground floor.
Area: 14,000 m².
My_tasks:
- Unitized curtain wall design for some specific areas.
- Subcontractor’s design managing for rains screen areas in ground floor and L09 Terrace.
- Steel ground Curtain Wall (Raico) design and workshop drawings.
- Workshop drawings for brackets, pressings and others.
- Builders Works drawings.
- Site visits to check installation and help installation team